Contest Brief

Assignment please See the attached file
Consider a project that consists of activities named A, B, ..., M. The following table gives the
predecessors and the duration in days of each of these activities.
Activity Predecessors Duration
A 5
B A 2
C B 2
D A 2
E C 10
F D,C 6
G C 13
H F,E,G 15
I A 2
J E 3
K F,E,I 6
L C,D 2
M D,J,I 3
1. Use the CPM method to find the critical path in this project. Show the details of the
calculation using the graphical representation seen during the lectures.
2. For each activity, give the impact on the completion date of the project if this activity
is delayed by 7 days. Justify your answers. Present the results in a table as follows:
Activity Impact, if delayed by 7 days Justification
A
B
C
D
E
F
G
H
I
J
K
L
M
1

Recommended Skills

Top entries from this contest

View More Entries

Public Clarification Board

  • aabb39187
    Contest Holder
    • 1 year ago

    please share it with me

    • 1 year ago
  • bsse1009
    bsse1009
    • 1 year ago

    I have almost finished the project. Bad luck :)

    • 1 year ago
    1. aabb39187
      Contest Holder
      • 1 year ago

      ok man

      • 1 year ago

How to get started with contests

  • Post your contest

    Post Your Contest Quick and easy

  • Get tons of entries

    Get Tons of Entries From around the world

  • Award the best entry

    Award the best entry Download the files - Easy!

Post a Contest Now or Join us Today!